TANAP Phase 1 is planned to be tested on April 15, TANAP Director General Saltuk Duzyol told journalists, Report informs citing Turkish media.
Duzyol noted that this part will be ready for gas transportation to Europe on July 1. According to him, as of February 1, the Phase 1 has been completed by 98%.
The Director General also said that 1.250 billion cubic meters of gas were transported via TANAP from June 30, 2018 to February 28, 2019.
According to him, the volume of gas to be transported via TANAP will be 2 bcm by the end of June, 4 bcm by the end of 2019.
TANAP shareholders are SGC (51%), SOCAR Turkey Energy (7%), BOTAS (30%), BP (12%).
Latest News
16:52
Nika Chitadze: Washington meeting key foundation for peace in South Caucasus
Foreign policy16:46
Washington agreements as foundation for new stage in US-Azerbaijan relations
Analytics16:14
Abbas Araghchi: Iran and Oman сlose to agreement on Strait of Hormuz
Other countries16:09
Bloomberg: Türkiye restricts passage of commercial ships into Black Sea
Region15:49
Tunnel under construction collapses in Türkiye, killing one, injuring another
Region15:30
ADNOC tanker attacked in Strait of Hormuz
Other countries15:16
Lionel Messi's father dies aged 68
Football15:03
Fitch affirms AFB Bank's rating at B with stable outlook
Finance14:47