Construction of Kashagan Gas Processing Plant to be completed in December 2026
Region
- 07 November, 2025
- 14:19
Construction of the Kashagan gas processing plant (GPP) will be completed in December 2026, said Alibek Zhamauov, chairman of the Board of QazaqGaz, Report informs referring to Kazakh media.
Equipment deliveries are expected to be completed in July 2026, and construction and installation of the integrated gas treatment facility is scheduled for October 2026.
He also cited gas export data for the first nine months of 2025, noting that Kazakhstan exported 3.9 billion cubic meters of gas. This exceeded the forecast by 28%. Domestic gas sales volumes were 100% fulfilled, reaching 13.6 billion cubic meters.
Latest News
00:05
Azerbaijan celebrates Ramadan
Religion00:04
Azerbaijan celebrates Novruz holiday
Cultural policy23:59
Infantino: 'We want the World Cup to take place as planned'
Football23:50
Zelenskyy: Ukraine's delegation going to peace talks in US, but not in full
Other countries23:39
Azerbaijan Embassy in Hungary to provide emergency consular support during holidays
Foreign policy23:27
Trump says he told Netanyahu not to attack energy fields in Iran
Other countries23:08
Chuck Norris hospitalized in Hawaii
Show business22:53
European powers, Japan pledge to secure Hormuz, stabilise energy markets
Other countries22:38