Construction of Aghdam–Khankandi railway reaches 48% completion
Infrastructure
- 22 September, 2026
- 11:09
Restoration of the Aghdam–Khankandi railway line, set to become one of Karabakh's new transport routes, is ongoing, Report informs, citing Azerbaijan Railways (ADY).
It was noted that 90% of design work and 48% of construction work have been completed.
The railway line will span 30.8 km and include 130 engineering structures: 6 bridges, 5 road underpasses, 2 pedestrian crossings, and 47 reserve crossings.
The concept designs of the Asgaran and Khojaly stations have already been finalized. Construction of the Khankandi Railway and Bus Terminal Complex is progressing rapidly and will serve hundreds of passengers daily.
Latest News
02:18
Kobakhidze: Broader opportunities emerge for South Caucasus cooperation
Region02:03
Bayramov, Petrova discuss gas supplies and Middle Corridor
Foreign policy01:59
Bayramov, Ishaq Dar review Azerbaijan-Pakistan ties
Foreign policy01:57
Bayramov, Sybiha discuss peace, stability and security challenges
Foreign policy01:05
Azerbaijan, Singapore discuss expanding bilateral cooperation
Foreign policy01:01
Azerbaijan, Colombia sign visa exemption agreement
Foreign policy00:59
Photo
Türkiye, Qatar eye deeper cooperation in energy, trade and defense
Region00:49
Azerbaijan, Hungary discuss bilateral ties and Azerbaijan-EU relations
Foreign policy00:47