Aghdam–Khankandi railway construction reaches 44% completion
Infrastructure
- 31 July, 2026
- 15:11
Work continues on the Aghdam–Khankandi railway line, one of the new transport routes in Karabakh, Azerbaijan.
According to Report, citing Azerbaijan Railways (ADY) CJSC, 90% of design work and nearly 44% of construction work have been completed.
The railway line will stretch 30.8 km and include 130 engineering structures: 6 bridges, 5 road underpasses, 2 pedestrian crossings, and 47 reserve crossings.
It was noted that the concept designs of the Asgaran and Khojaly stations have already been finalized, while construction of the Khankandi Railway and Bus Terminal Complex is progressing rapidly.
Latest News
00:10
Azerbaijan marks Khankandi, Khojaly, Khojavand and Aghdara Cities Day
Karabakh00:00
Three years pass since Azerbaijan announced restoration of sovereignty
Karabakh17:51
Photo
Heydar Aliyev International Airport to operate in enhanced mode ahead of Formula 1
Infrastructure17:41
Photo
Turkic Union of Composers established in Baku
Cultural policy17:21
Photo
Azerbaijan, Germany mull co-op in climate sphere
Foreign policy17:02
T-VINE: Baku became one of most recognizable Formula 1 venues
Formula 116:41
Aston Martin to unveil final upgrade for AMR26 car at Baku Grand Prix
Formula 116:23
23 hours and 43 minutes: Sovereignty, end of separatism, and new realities in South Caucasus – COMMENTARY
Analytics16:00