bp: Drilling of first production well on ACE platform is nearing completion
Energy
- 19 February, 2024
- 12:53
Drilling of the first production well on the Azeri Central East (ACE) platform, which is being built in the Azeri-Chirag-Gunashli (ACG) oil and gas block of fields located in the Azerbaijani sector of the Caspian Sea, is nearing completion, Bakhtiyar Aslanbayli, bp's Vice President for the Caspian region, Communications and External Affairs, told Report.
According to him, three production wells are planned to be drilled on the ACE platform this year: "The process of drilling the first production well is almost complete."
The Vice President said that the first oil from the first well will probably be produced during the 1st quarter, and this will be announced: "Besides, there will be two more production wells."
Latest News
15:19
Photo
Presidents Ilham Aliyev and Serdar Berdimuhamedov visit Bulbul's House-Museum in Shusha
Domestic policy15:10
Over 9,100 residents evacuated, schools suspended as rainstorms hit SW China
Other countries15:05
EU, Kazakhstan sign package of agreements in Brussels during Tokayev's visit
Region15:00
Uzbekistan's president to visit Belarus
Other countries14:50
Casualties reported as Russia attacks Kryvyi Rih
Other countries14:44
Baku to host European Championship in Free Pyramid
Individual sports14:31
EU special rep for South Caucasus to visit Azerbaijan - EXCLUSIVE - UPDATED
Foreign policy14:31
Ruginienė resigns as Lithuanian prime minister
Other countries14:25
Photo