Amount of expenditure on SGC announced
Energy
- 30 May, 2019
- 11:35
Up to late April, $33 billion in total was invested in the Southern Gas Corridor (SGC), SGC Director General Afghan Isayev said at the 26th International Caspian Oil & Gas Conference.
According to him, $18.8 billion was spent on Shahdeniz 2, which costs $21.9 in total. Works on Shahdeniz 2 have been completed by 92.6%.
He said that expenditures on Southern Caucasus Pipeline amounted to $4.3 billion. The project costs $4.5 billion.
TANAP spent $6.2 billion as at the end of April. The project costs $7 billion. 99% of works on TANAP has been completed.
TAP, which totally costs EUR 4.6 billion, spent EUR 3.6 billion. 87.5% of works on TAP has been completed.
Latest News
00:19
Azerbaijan marks 34th anniversary of Aghdaban massacre
Domestic policy23:55
Madagascar declares state of emergency over energy situation due to Iran war
Other countries23:50
Iran condemns Trump's threat to destroy Iranian civilization
Region23:37
Azerbaijan beach soccer team beats Moldova in second friendly
Football23:29
Photo
TÜRKPA Economic Cooperation Commission holds 13th meeting in Baku
Foreign policy23:17
Trump will pursue stability with China's Xi in May meeting, USTR Greer says
Foreign policy23:10
Bahrain says UN Security Council failed to act after Hormuz resolution veto
Other countries23:04
EIA projects Azerbaijan's 2027 daily oil output at 540,000 barrels
Energy23:01