75% of pipes for Greece section of TAP received
- 29 June, 2017
- 13:19
Baku. 29 June. REPORT.AZ/ 75% of pipes for construction of Greece section of the Trans-Adriatic Pipeline (TAP), which will transport Azerbaijani gas to Europe, have been received.
Report informs, Rikard Scoufias, TAP Country for Manager Greece said at today's "21st roundtable with the Government of Greece" event.
According to him, 24.000 out of total 32.000 pipes have been received.
Notably, TAP, which is a part of Southern Gas Corridor project, will initially transport annual 10 bln cubic meters of the gas produced within 'Shah Deniz 2' project, to Europe. This pipeline will join TANAP (Trans Anatolian) pipeline in Kipoi territory on Turkey-Greece border and cross Greece, Albania and the Adriatic Sea before going onshore in southern Italy.
After reviewing various selection options during two years, on June 28, 2013, 'Shah Deniz' Consortium has officially declared selection of the TAP project. The pipeline is 878 kilometers long, which 550 km will cover Greece, 215 Albania, 105 Adriatic Sea and 8 km Southern Italy. Highest point of the pipeline will be in the mountains of Albania (1 800 meters), the lower part (-820 meters) beneath the sea.
TAP's groundbreaking ceremony was held in Thessaloniki, Greece on May 17, 2016. Azerbaijani gas will be delivered to Europe on 2020.
BP (20%), SOCAR (20%), 'Snam S.p.A.' (20%), 'Fluxys' (19%), 'Enagas' (16%) and 'Axpo' (5%) companies acting as TAP shareholders.